Proceed to IC
Readiness ≥80 and confidence ≥75%, with no hard stop.
METHODOLOGY / RULESET 0.1
The current data-center screening model makes category weights, confidence logic, thresholds, and hard stops inspectable.
INVESTMENT READINESS
Capacity, utility commitment, and energization certainty.
25%Land control, entitlements, and environmental readiness.
15%Efficiency, redundancy, and design readiness.
15%Contracted demand and tenant commitments.
20%Underwritten yield and funding certainty.
15%Construction commitments and delivery stage.
10%Readiness is a weighted 0–100 score computed from structured intake. Unknown categorical statuses map to zero. These provisional rules have not been calibrated as an institutional rating.
EVIDENCE CONFIDENCE
A strong input is still an assumption until its evidence is examined.
For each category, a reviewed source counts when both a claim and source reference are recorded. Confidence uses source-coverage bands, then applies the same category weights.
Confidence is a source-coverage indicator, not a statistical probability or assurance that a document is authentic.
SCREENING OUTPUT
HARD STOPS
A blocked site-permitting status forces a V4 screening outcome.
Indicative power status with zero secured capacity forces V4.
Analyst-marked contradictions reduce the affected category’s readiness score by 25 points and force V4.
REVIEW AND RELIANCE
Verdict prepares the case for review. Analysts and committees remain responsible for evaluating it.
Review status is assigned by an analyst. The current product does not automatically extract claims, independently verify documents, or issue a signed institutional rating.
The memorandum reflects the current workspace. It requires analyst validation and committee approval. Broader rating methods and institutional governance remain planned.
THE NEXT DECISION
Explore the live data-center demonstration or speak with the co-founders about financial diligence, infrastructure, credit, and portfolio intelligence.